Vale, Frood Strobie 230kV/69kV Substation Feasibility Study

Location : Sudbury, Ontario

Year : 2016

Client : Vale

Project type : Feasibility study and cost estimations

The installation includes: 

  • one (1) 230/69kV transformer 230FS2T2
  • one (1) 230kV breaker 230FS2B1
  • one (1) 72kV main breaker 69FS2B2
  • one (1) 72kV tie breaker 69FS2BXX
  • one (1) 72kV disconnect switches 69FS2D6
  • 69 kV tower structure and associated foundations
  • two (2) 72kV feeds and associated breakers (69FS2B21, 69FS2B23) and switches (69FS2D21-B, 69FS2D23-B)
  • power and control cabling, grounding, control building repairs, and protection and control equipment upgrade
  • 2 FroodStobie2 locates A